BE IT ENACTED BY THE TOWN BOARD OF THE TOWN OF CANDOR AS FOLLOWS:
SECTION 1.0 - TITLE, STATUTORY AUTHORIZATION AND PURPOSE
1.1 Title - This local law shall be known as the "Development and operating of Seasonal Use
Roads Law".
1.2 Statutory Authorization - This local law is adopted under the authority of section 64(23)
and Section 130(1) of the Town Law of the State Of New York.
1.3 Purpose - It is the purpose of this local law to promote the safety, health and general
welfare of the residents of the Town of Candor by regulating the issuance of building
permits for any structure on seasonal use roads which may not provide 12 month access
for fire and other emergency vehicles for the inhabitants or occupants of such structures.
SECTION 2.0 - DEFINITIONS
2.1 "Seasonal Use Road" roads designated by Superintendent of Highways as seasonal shall
mean seasonal use road as defined under section 205(a) of the Highway Law (see Town
Clerk for listing of seasonal use roads).
2.2 "Building Permit" shall mean a permit issued for the erection or installation of any
structure regulated by the New York State Uniform Fire Prevention and Building Code,
this local law and/or other Local Law of the Town of Candor regulating such construction
or installation.
2.3 Minimum Maintenance Roads – refer to seasonal use road
2.4 Limited Use Highway – refer to seasonal use road
2.5 "Applicant" shall mean the owner or owners of record of any real property for which a
building permit is sought and, if applicable, any person or persons, purchasing such
property by recorded land contract.
SECTION 3.0 - GENERAL PROVISIONS
3.1 Conditions for issuance of building permit. Building permits may be issued in the Town
of Candor on any seasonal use road meeting one of the following requirements:
- Type U (Utility) Structure as defined in the New York State Fire Prevention and
Building Code including hunting and fishing cabins defined as a cabin, camp or
lean-to or other similar structure designed for occasional occupancy for hunting,
fishing, or other recreational purposes.
- The applicant shall be lawfully entitled to apply for a building permit and shall
have paid the requisite fee therefore.
- The applicant shall have met all requirements, other than with respect to the
seasonal use road, for the issuance of a building permit as mandated by the
New York State Fire Prevention and Building Code and any other federal, state
or local law with respect to the issuance thereof at the time of application.
- All other building types as defined in the New York State Fire Prevention and
Building Code, including changing use and occupancy classifications, shall meet
all the following requirements and conditions:
- The applicant shall be lawfully entitled to apply for a building permit and shall
have paid the requisite fee therefore.
- The applicant shall have met all requirements, other than with respect to the
seasonal use road, for the issuance of a building permit as mandated by the
New York State Fire Prevention and Building Code and any other federal, state
or local law with respect to the issuance thereof at the time of application.
- The applicant shall submit at the time of filing application for a building
permit, a request for the conversion of the seasonal use road to a 12 month
maintained road on the form prescribed for such purpose, or if none, by letter,
stating the name of the applicant, location of proposed development, name of
road sought to be opened, distance in linear feet of seasonal use road sought to
be opened, amount of assessed improvements currently located along said
road, if any, amount of anticipated assessed valuation for proposed
development under the building permit application and statement that there is
no other access to proposed development over any other 12 month maintained
roadway.
- The market value of improvements along the seasonal use road to be opened
shall be no less than the amount specified in the “Schedule of Fees and
Values” per 0.2 mile, as measured from the nearest year round regularly
maintained highway, including the improvements to be erected under the
applicant's building permit.
- The length of seasonal use road to be converted to a 12 month maintained road
must connect another 12 month maintained highway or the Town of Candor
shall prior to issuance of a building permit be given an easement for a turn
around by the applicant or any third party of a size and at a location to be
determined by the Town Highway Superintendent. Such easement shall be in
recordable form. Applicant shall pay all costs of obtaining and recording the
easement. The form and content of the easement shall be acceptable to the
Town.
- No certificate of compliance shall be issued pursuant to any building permit
issued for development along a seasonal use road until satisfaction of the
requirements of these conditions and verification is filed with the Town Clerk
that the market value requirements set forth in paragraph (4) of these
conditions have been met. Applicant at the time of submitting his request to
open the seasonal use road must execute an acknowledgement of this condition
and a release to the Town of Candor for any liability or damages in connection
with this condition, the form of the release shall be established by the Town
Board.
- No seasonal use road shall be opened or be required to be worked by the
Town, for year round access, until a certificate of compliance is issued by the
Code Enforcement Officer. In the event no certificate of compliance is issued,
the Town of Candor shall have no obligation to open the seasonal use road for
year round access.
- No certificate of occupancy shall be issued for improvements located on a
seasonal use road between October 1 and April 1.
3.2 Board Review
- The Town of Candor shall review the application to open any seasonal use road.
Applications must be submitted at least two weeks prior to a regular Board
meeting following submission of the application by the Code Enforcement officer
to the Town Clerk. Such application shall only be submitted after the Code
Enforcement Officer shall have determined that except for the location of the
proposed development on the seasonal use road, the building permit would be
issued. In such case, the application to open the seasonal use road shall be
submitted as soon as practicable by the Code Enforcement Officer after such
determination is made.
- No seasonal use road shall be converted to 12 month use if, in the sole opinion of
the Town Highway Superintendent, the 12 month use of the road would create
any undue risk to the health or safety of the public using such road and/or to the
employees of the Town of Candor maintaining it. Such opinion shall be
absolutely final and binding on the applicant.
3.3 Limitations on opening seasonal use roads
- The Town of Candor shall in no event be required to open more than one mile of
seasonal use road under this policy in any single calendar year. In the event
application to open seasonal use roads exceeds this limitation, applications will be
acted upon on a first come, first serve basis. Unsuccessful applicants shall receive
no priority on resubmission in a subsequent application.
3.4 Town’s right to open seasonal use road
- The Town's adoption of this local law shall in no way limit the right of the Town
Board on its own elect to open any seasonal use road to 12 month use, if in the
discretion of the Town Board, it is deemed in the best general interest of the
public to do so.
SECTION 4.0 - CONFLICT AND INTERPRETATION
4.1 Interpretation of State Code
- Whenever possible, this local law shall be interpreted in a manner compatible
with the New York State Uniform Fire Prevention and Building Code, however,
in the event of any conflict or incompatible interpretation, the stricter
requirements of the two shall apply with respect to the issuance of a building
permit.
4.2 Saving Clause
- If any section, paragraph, subdivision or provision of this local law shall be
adjudged invalid or held unconstitutional, the same shall not affect the validity of
this local 1aw as a whole or any part or provision thereof other than the part so
decided to be invalid or unconstitutional.
4.3 Effective Date
- After approval by the Candor Town Board and filing with the State of New York.